WORKSHOP FOR THE CREATION
OF NEW NUMBERING PLANS IN AFRICA
Cotonou, Benin, 30 June - 4 July 2003 |
 |
RECOMMENDATIONS SYNTHESIS
I
� Justification of the change
+ |
Saturation of the existing plan; |
+ |
Introduction of new services and/or new operations; |
+ |
Harmonization of the format of the numbers. |
Il
- Rules to be followed in conformity with ITU recommendation
+ |
Establish a simple plan to switch from old to new numbers; |
+ |
Target period plan: 30 years; |
+ |
Harmonize the emergency numbers; |
+ |
Optional phone book registration with the customers'
agreement; |
+ |
Set up a coordination team between the authority an the
operator for follow-up of project; |
+ |
Assign the low figures to fixed lines and higher figures
to mobile lines; |
+ |
Take into consideration the population and the economic
forecasts of the areas when distributing the numbers; |
+ |
Consider taking a technical cut rather than an
administrative or a political cut; |
+ |
Migrate the new services in the range of the 800 and 900
numbers with possibility of using 9 X and 0 for mobile lines; |
+ |
Choose preferably a closed-circuit plan; |
+ |
Reserve number 112 for emergency for mobile lines as
recommended at international level. |
III
- Implementation
+ |
Establish a plan of implementation in coordination with
the authority (ies) and the operator(s); |
+ |
Prepare a communication plan for the operators, the press,
international organizations, customers' etc..; |
+ |
Foresee available funding to carry out the communication plan; |
+ |
Prepare
pre-registered redirecting messages for the numbers not included in the
new plan; |
+ |
During low traffic periods, foresee sufficiently in
advance, a simulation switching system to be able to fix possible
failures. |
IV
- Management Plan
+ |
Harmonize the management plan to be easily applicable by
the regulator and by the operator. |
|